The Queens facility

126-02 82nd Avenue, Kew Gardens. One of four borough facilities that will replace Rikers, near the Queens courts and the families and services people rely on.

Track Queens commitments Construction updates

Rendering of the Queens facility beside a park

The building

About the Building

The Queens facility will hold people with cases from Queens close to the borough's courts, so they can stay connected to lawyers, family, and services while their case moves forward.

Rendering of the facility seen from across the street, with trees and a lawn
View from the street
Where is it?
126-02 82nd Avenue, Kew Gardens
Get directions (opens in a new tab)
How big is it?
1,040 beds, including 450 for women and gender-expansive people
Community space
25,000 sq ft of community space, already built as part of the Queens garage in 2023, distinct from the jail and with its own entrance. Its community purposes and services will be developed with local feedback.
When will it open?
Scheduled to open in 2031.
Who do I contact about construction?
Community Construction Liaison: (646) 940-0812, [email protected].
When are community meetings?
Dates and advisories are posted with the construction updates below.

The plan

Where this fits in The plan

The four borough facilities are one part of the plan to close Rikers. The others change how the jails are run, keep more people out of jail, and plan for the island's future.

  1. This facility

    Safer facilities

    Opening new facilities that are safer and more humane, in locations closer to courts and public transportation. This facility is one of them.

  2. Modernizing the DOC

    Restructuring and modernizing the Department of Correction to ensure that the operational challenges faced at Rikers Island are not transferred to the new facilities

  3. Fewer People in Jail

    Fewer case delays, targeted release, diversion, and fewer people returning to jail mean fewer people held, for less time.

  4. The future after closing

    Planning for the Future Reuse of Rikers Island, with a focus on climate resilience, sustainability and renewable energy.

Commitments

What the city promised Queens

The Points of Agreement for Queens, at the site and across the neighborhood. Open any commitment for the latest update, budget, and original language. Statuses are from the city's November 2026 update.

Open in the tracker
  • Delivered
  • In progress
  • Pending

At the facility site

  • POA 1 Reduced Height and Density of the Jail DeliveredComplete

    Latest update

    Plans include significant reduction from initial proposals. The design-build teams will continue to seek further opportunities for efficiency in construction.

    Budget

    POA 1 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    The final approved maximum building height is 195 feet and the maximum density is a Floor Area Ratio (FAR) of 3.71. This represents a significant reduction from the initial proposal in the Draft Scope of Work, which proposed a height of 310 feet and a density of 5.6 FAR.

    Read the full commitmentSee it on the tracker

  • POA 2 Provision of Community Facility or Commercial Space (25,000 sq ft) DeliveredWhite box construction completed by DDC

    Latest update

    The Queens Garage project was completed in 2023, including 25,000 square feet of "white box" space for future use as a community facility or retail space, currently undefined. The use of this space will be determined at a later time with input from the community.

    Budget

    $80.1 million

    Original commitment

    The project will include the construction of 25,000 square feet of community facility or commercial space. The City will work with the Council and the community to shape the use of this space, including consideration of the use of a soup kitchen.

    Read the full commitmentSee it on the tracker

  • POA 3 Design Consultation DeliveredComplete

    Latest update

    The city held a series of community design input workshops and Queens Community Board 9 meetings in 2025-2026 to collect input on the Queens Facility design as it developed. The city continues to meet regularly with Council members, Community Boards, community members, and advocates in Queens to discuss construction updates, and quality of life impacts.

    Budget

    POA 3 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    Upon ULURP completion, the City will provide regular updates on delivery schedule, design, and construction developments and engagement on programmatic progress to Council Members in each respective borough. The City will reconvene the Neighborhood Advisory Committees in Queens, Brooklyn, and the Bronx and the Joint Task Force in Manhattan within 60 days of ULURP passage and will hold regular meetings with updates on time lines, plans, and the like. Finally, DDC and the program management consultant will hold hands-on design engagement workshops that are timed in order to ensure community input is included in the eventual RFP(s).

    Read the full commitmentSee it on the tracker

  • POA 4 Parking In progressIn progress - included in facility design-build contract

    Latest update

    The Queens Garage project was completed in 2023 including 600+ public parking spaces. In addition, accessory parking spaces for authorized vehicles will be included in the new facility. The city reduced program redundancies across all four sites including a reduction in the required number of accessory parking spaces in Queens to 100 spaces, thus reducing the cost of the project. The revised parking is analyzed and reflected in the April 2024 technical memorandum available on CEQR Access.

    Budget

    POA 4 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    The project will include a new 676 space public parking garage, a net increase of 150 parking spaces from the current configuration. In addition, 605 accessory parking spaces for DOC staff and authorized service providers will be provided below- grade in order to limit the impact to on- street parking in the community. Parking for the DOC staff will be offered at no cost in order to ensure that on-street parking is not incentivized.

    Read the full commitmentSee it on the tracker

  • POA 5 Construction Coordination (Community Construction Liaison) DeliveredComplete

    Latest update

    Queens Community Construction Liaison CCL Mobile: (646) 940-0812 Email: [email protected] (current address - trailer) 126-02 82nd Ave, Kew Gardens, NY 11415

    Budget

    POA 5 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    DDC will establish an office near each project site to provide site-specific information and address community complaints and concerns.

    Read the full commitmentSee it on the tracker

  • POA 6 Street Trees In progressIn progress - included in facility design-build contract

    Latest update

    The protection of street trees was included as requirement in the Queens Garage and Community Space and Queens Dismantle/Swing Space contracts and is included as a requirement in the Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 6 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    Existing street trees will be protected, and all work would be performed in compliance with Local Law 3 of 2010 and the NYC Parks Tree Protection Protocol approved by the NYC Parks Borough-specific Forester, to minimize potential adverse impacts to existing trees that will remain in place.

    Read the full commitmentSee it on the tracker

  • POA 7 Air Quality and Noise Monitoring In progressIn progress - included in facility design-build contract

    Latest update

    Air quality and noise monitoring has been included as a requirement in the Queens Garage and Community Space and Queens Dismantle/Swing Space RFPs, and will be included as a requirement in the Queens Facility RFP. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 7 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    The DDC will conduct air quality and noise monitoring to limit community impacts and provide for compliance with all applicable regulations.

    Read the full commitmentSee it on the tracker

  • POA 8 Traffic Mitigation In progressIn Progress

    Latest update

    In Progress

    Budget

    POA 8 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    A Construction Transportation Monitoring Plan (CTMP) will be initiated at the start of construction for the project work area and, if necessary, additional traffic control measures will be implemented.

    Read the full commitmentSee it on the tracker

  • POA 9 Protecting Open Space In progressIn progress - included in facility design-build contract

    Latest update

    Open space resources were not used for staging or other construction activities during the Queens Garage and Dismantle projects. As defined in the Queens Facility contract, the project design-builder will not be permitted to use open space resources for staging or other construction activities during facility construction.

    Budget

    POA 9 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

    Original commitment

    No open space resources will be used for staging or other construction activities.

    Read the full commitmentSee it on the tracker

  • POA 13 New Sewers in Kew Gardens In progressOngoing

    Latest update

    The hydraulic analysis was completed in January 2020 and DDC/DEP are in conversations about potential sewer system upgrades in the area. The environmental review of the project found that the increase in wastewater flow resulting from the approved project would not create a significant adverse impact on the city's combined sewer system or the sewage treatment system.

    Budget

    Pending final determination by DEP.

    Original commitment

    A hydraulic analysis will be conducted during design and if it is determined that the existing sewer system is incapable of supporting the increase in wastewater flow, the existing sewer system will be upgraded.

    Read the full commitmentSee it on the tracker

In the neighborhood

  • POA 10 Invest in Capital Improvements at PS 99 and PS 139 DeliveredComplete

    Latest update

    PS 99: Gym and auditorium upgrades were completed in September 2024, the playground was forecasted to be complete in May 2025. PS 139: Security cameras are forecasted to be installed by the end of the 2024-2025 school year of the 2024-2025 school year.

    Budget

    Not stated in the latest update

    Original commitment

    The School Construction Authority (SCA) will invest in capital improvements to renovate the auditorium and gymnasium, renovate the school yard, and install interior and exterior security cameras at P.S. 99 and to install security cameras in the school yard at P.S. 139.

    Read the full commitmentSee it on the tracker

  • POA 11 New uniformed officers for the 102nd Precinct In progressIn Progress

    Latest update

    Since January 2020, we have assigned 83 UMOS to the 102 from the Police Academy. The 102 Precinct currently has 135 Police Officers, with a hard ceiling of 165. The Department, through the Strategic Initiatives Bureau and Crime Control Strategies are constantly assessing which Precincts require more manpower from Police Academy graduations by looking at crime stats, 911 calls, 311 calls, and response times.

    Budget

    New Police Officers would have an annual pay of $60,884 (this includes a base salary of $55,942 plus differential pay, holiday pay, and a uniform allowance).

    Original commitment

    NYPD has added 6 officers from its October graduating class to the 102nd precinct. NYPD will continue to evaluate the need for more resources at the 102nd Precinct and will increase the number of officers assigned as needed.

    Read the full commitmentSee it on the tracker

  • POA 12 Improving Lighting in the Austin Street Underpass DeliveredComplete

    Latest update

    Complete

    Budget

    $80 thousand

    Original commitment

    DOT will install a lighting upgrade for Austin Street Underpass, defined as Austin Street under Union Turnpike between 80 Road and 78th Avenue.

    Read the full commitmentSee it on the tracker

  • POA 14 Monitoring Flooding Complaints In progressOngoing

    Latest update

    DEP continues to monitor flooding complaints to ensure jail construction will not exacerbate flooding conditions.

    Budget

    Performed with existing resources.

    Original commitment

    DEP will track street flooding complaints in the area surrounding the Queens facility and ensure jail construction will not exacerbate flooding conditions.

    Read the full commitmentSee it on the tracker

  • POA 15 Additional Trash Cans DeliveredComplete

    Latest update

    Complete

    Budget

    Performed with existing resources.

    Original commitment

    The Department of Sanitation (DSNY) will work with the Council Member to identify locations for and place 20 new trash cans in Council District 29.

    Read the full commitmentSee it on the tracker

  • POA 16 Invest in Upgrades to Queens Community House DeliveredComplete

    Latest update

    The organization used $66,000, to upgrade kitchen by moving walls, purchasing refrigerator, food warmer, and freezer. They used left over funds to purchase computers and chrome books.

    Budget

    Contractually funded at $207,000, one-time funding of $66,000 for upgrades

    Original commitment

    $66,000 one-time funding will be provided to upgrade existing kitchen infrastructure at 8002 Kew Gardens Road. Funding will also be added to support the expansion of the senior lunch program.

    Read the full commitmentSee it on the tracker

Construction

Current Construction updates

Current construction advisories, community meeting dates and project updates are posted on the borojails website.

Questions

Queens questions

Why is the city building a facility in Queens?

Closing Rikers means replacing it with a smaller system in the boroughs. A Queens facility keeps people near the Queens courts, their lawyers, and their families, instead of on an island that is hard to reach.

When will the Queens facility open?

The Queens facility is scheduled to open in 2031.

How will the Queens community space be used?

25,000 square feet of community space, already built as part of the Queens garage in 2023, is distinct from the jail and has its own entrance. Its community purposes and services will be developed with local feedback.

Who do I contact about Queens construction?

The Queens Community Construction Liaison: (646) 940-0812, [email protected].

All questions and answers

Archive

From the Queens archive

Construction bulletins, monitoring reports and meeting materials the program published about this site, kept for the record.

427 items, newest first · page 1 of 54

Open the full archive in Resources

all four

Borough-based jails

A fundamental component to the closure of Rikers Island is developing the capacity to house individuals in custody of the Department of Correction off-island, in facilities that are safer and more humane.

See all four facilities Read the full report