Skip to content
NYCClosing Rikers

a smaller system, closer to home

The Brooklyn facility

275 Atlantic Avenue. One of four borough facilities that will replace Rikers, near the Brooklyn courts and the families and services people rely on.

Track Brooklyn commitments Construction updates

Rendering of the Brooklyn facility tower at a street corner

The building

About the Building

The Brooklyn facility will hold people with cases from Brooklyn close to the borough's courts, so they can stay connected to lawyers, family, and services while their case moves forward.

Rendering of the main entrance: a glass lobby under the tower, with flags, planters, trees and people on a wide plaza
Entry plaza on Atlantic Avenue
Where is it?
275 Atlantic Avenue, Brooklyn
Get directions (opens in a new tab)
How big is it?
1,040 beds
Community space
30,000 sq ft of street-level community space, distinct from the jail and with its own entrance. Its community purposes and services will be developed with local feedback.
When will it open?
Scheduled to open in 2029.
Who do I contact about construction?
Community Construction Liaison: (516) 846-9314, [email protected].
When are community meetings?
Dates and advisories are posted with the construction updates below.

The plan

Where this fits in The plan

The four borough facilities are one part of the plan to close Rikers. The others change how the jails are run, keep more people out of jail, and plan for the island's future.

  1. This facility

    Safer facilities

    Opening new facilities that are safer and more humane, in locations closer to courts and public transportation. This facility is one of them.

  2. Modernizing the DOC

    Restructuring and modernizing the Department of Correction to ensure that the operational challenges faced at Rikers Island are not transferred to the new facilities

  3. Fewer People in Jail

    Fewer case delays, targeted release, diversion, and fewer people returning to jail mean fewer people held, for less time.

  4. The future after closing

    Planning for the Future Reuse of Rikers Island, with a focus on climate resilience, sustainability and renewable energy.

Commitments

What the city promised Brooklyn

The Points of Agreement for Brooklyn, at the site and across the neighborhood. Open any commitment for the latest update, budget, and original language. Statuses are from the city's November 2026 update.

Open in the tracker
  • Delivered
  • In progress
  • Pending

At the facility site

  • POA 1 Reduced Height and Density of the Jail DeliveredComplete

    Latest update

    Plans include significant reduction from initial proposals. The design-build teams will continue to seek further opportunities for efficiency in construction.

    Budget

    POA 1 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    The final approved maximum building height is 295 feet and the maximum density is a Floor Area Ratio (FAR) of 11.9. This represents a significant reduction from the initial proposal in the Draft Scope of Work, which proposed a height of 430 feet and a density of 20.1 FAR.

    Read the full commitmentSee it on the tracker

  • POA 2 Provision of Community Facility (30,000 sq ft) In progressIn progress - included in facility final design documents

    Latest update

    The Brooklyn Facility contract includes the requirement to provide 30,000 square feet of space for future use as a community facility or retail space, currently undefined. The use of this space will be determined at a later time with input from the community.

    Budget

    POA 2 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    The project will include the construction of 30,000 square feet of community facility. The City will work with the Council and the community to shape the use of this space. This space will primarily front Atlantic Avenue, which will provide an active and lively streetscape in keeping with the commercial corridor

    Read the full commitmentSee it on the tracker

  • POA 3 Design consultation DeliveredComplete

    Latest update

    The city held a series of community design input workshops and Brooklyn Community Board 2 meetings in 2023-2024 to collect input on the Brooklyn Facility design as it developed. The city continues to meet regularly with Councilmembers, Community Boards, community members, and advocates in Brooklyn to discuss construction updates, and quality of life impacts.

    Budget

    POA 3 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    Upon ULURP completion, the City will provide regular updates on delivery schedule, design, and construction developments and engagement on programmatic progress to Council Members in each respective borough. The City will reconvene the Neighborhood Advisory Committees in Queens, Brooklyn, and the Bronx and the Joint Task Force in Manhattan within 60 days of ULURP passage and will hold regular meetings with updates on time lines, plans, and the like. The City will also engage the residents of 265 State Street, 199 State Street, 96 Schermerhorn, and 87 Smith Street to address ongoing community concerns around building form and curb cut locations. Finally, DDC and the program management consultant will hold hands-on design engagement workshops that are timed in order to ensure community input is included in the eventual RFP(s).

    Read the full commitmentSee it on the tracker

  • POA 4 Parking In progressIn progress - included in facility final design documents

    Latest update

    The city reduced program redundancies across all four sites including a reduction in the required number of accessory parking spaces in Brooklyn to 83 spaces for authorized city vehicles including 5 parking spaces dedicated to the NYPD sally port, thus reducing the cost of the project. The revised parking is analyzed and reflected in the March 2024 technical memorandum available on CEQR Access.

    Budget

    POA 4 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    292 accessory parking spaces for DOC staff and authorized service providers will be provided below-grade in order to limit the impact to on-street parking in the community.

    Read the full commitmentSee it on the tracker

  • POA 6 Outdoor Recreation Space on the Roof In progressIn progress - included in facility final design documents

    Latest update

    There are outdoor recreation areas in each housing unit that provide access to daylight and fresh air. Additionally, people in custody will have access to the horticulture program which includes a greenhouse and an outdoor area on the roof at level 14. Remaining roof space is occupied by necessary mechanical and HVAC equipment, as well as photovoltaic panels and a green roof as required by DEP.

    Budget

    POA 6 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    The City will explore utilizing available rooftop area to provide open-air outdoor recreation at the Brooklyn facility unoccupied by Mechanical, Electrical, and Plumbing equipment (MEP).

    Read the full commitmentSee it on the tracker

  • POA 7 Ingress/Egress from the Facility DeliveredComplete

    Latest update

    Complete

    Budget

    Complete (No budget allocation for this item)

    Original commitment

    The City commits to undertake a traffic study to identify potential alternate egress/ingress proposals for the facility that might further minimize traffic impacts associated with the proposed facility.

    Read the full commitmentSee it on the tracker

  • POA 8 Construction coordination (Community Construction Liaison) DeliveredComplete, will continue through construction completion

    Latest update

    Brooklyn Community Construction Liaison CCL Mobile: (516) 846-9314 Email: [email protected] 395 Atlantic Ave. Brooklyn, NY 11217

    Budget

    POA 8 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    DDC will establish an office near each project site to provide site-specific information and address community complaints and concerns.

    Read the full commitmentSee it on the tracker

  • POA 9 Street Trees In progressIn progress - included in facility design-build contract

    Latest update

    The protection of street trees was included as requirement in the Brooklyn Dismantle contract and is included as a requirement in the Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 9 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    Existing street trees will be protected, and all work would be performed in compliance with Local Law 3 of 2010 and the NYC Parks Tree Protection Protocol approved by the NYC Parks Borough-specific Forester, to minimize potential adverse impacts to existing trees that will remain in place.

    Read the full commitmentSee it on the tracker

  • POA 10 Air Quality and Noise Monitoring In progressIn progress - included in facility design-build contract

    Latest update

    Air quality and noise monitoring was conducted during the Brooklyn Dismantle project, and is included as a requirement in the Brooklyn Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 10 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    The DDC will conduct air quality and noise monitoring to limit community impacts and provide for compliance with all applicable regulations.

    Read the full commitmentSee it on the tracker

  • POA 11 Traffic Mitigation In progressIn progress - included in facility design-build contract

    Latest update

    A CTMP was included as a requirement in the Brooklyn Dismantle contract and is included in the Facility Design-Build contract. Part of the CTMP will be a monitoring plan for traffic which could provide for additional traffic control measures if deemed necessary.

    Budget

    POA 11 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    A Construction Transportation Monitoring Plan (CTMP) will be initiated at the start of construction for the project work area and, if necessary, additional traffic control measures will be implemented.

    Read the full commitmentSee it on the tracker

  • POA 12 Protecting Open Space In progressIn progress - included in facility design-build contract

    Latest update

    Open space resources were not used for staging or other construction activities during the Brooklyn Dismantle project. As defined in the Brooklyn Facility contract, the project design-builder will not be permitted to use open space resources for staging or other construction activities during facility construction.

    Budget

    POA 12 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

    Original commitment

    No open space resources will be used for staging or other construction activities.

    Read the full commitmentSee it on the tracker

  • POA 13 Preserve a portion of the Justice Mandala mural DeliveredComplete

    Latest update

    A conservator evaluated the Justice Mandala murals and provided a scope of work and draft cost estimate for salvaging the mural in part or in whole. It was determined in conversations with the artist organization that DOC would document the mural through photographs and narrative but that the mural would be dismantled with the existing facility. The new Brooklyn facility is part of the city's Percent for Art program.

    Budget

    Complete (DDC and DOC documented the mural. No budget allocation for this item.)

    Original commitment

    A portion of the Justice Mandala mural from the State Street side of the current Brooklyn Detention Complex will be salvaged and re- installed in a public place with description of artwork and its history.

    Read the full commitmentSee it on the tracker

In the neighborhood

  • POA 5 Streetscape improvements In progressOngoing

    Latest update

    DOT added the CitiBike station on State Street. DOT will explore Atlantic Avenue streetscape improvements and traffic study on Smith St.

    Budget

    Ongoing

    Original commitment

    The Department of Transportation (DOT) will commit to determining feasibility for safety and bike infrastructure on State Street. DOT will work with the Council Member to evaluate the availability of curb space to accommodate a Citibike station, subject to parking constraints and other street regulations. DOT will explore options to improve the Atlantic Avenue streetscape and will work with the Neighborhood Advisory Committee to develop a package of streetscape improvements surrounding the Brooklyn Borough-Based Jail site. DOT will conduct a traffic study of Smith Street between Fulton and Atlantic Avenue.

    Read the full commitmentSee it on the tracker

  • POA 14 Expansion of pre-arraignment diversion programming In progressOngoing

    Latest update

    MOCJ recently expanded Project Reset to be available citywide in 2022. MOCJ works with stakeholders to expand pre-arraignment diversion programming. In November 2023, Project Reset expanded to offer Rapid Reset in the Bronx and Manhattan. Rapid Reset builds on our pre-arraignment services by offering courthouse-based diversion programming to eligible individuals, this avoids lengthy court proceedings and advances MOCJ restorative justice goals.

    Budget

    In FY26 the program has been funded for a baselined amount of $4,005,620 annually.

    Original commitment

    The City will work with the District Attorneys and Courts to expand pre-arraignment and post-arraignment diversion, offering individuals the opportunity to avoid prosecution and collateral consequences of criminal justice involvement. Through the completion of alternative diversionary programming provided via this funding, individuals will be able to avoid prosecution by the District Attorney and have their arrests sealed, leaving no criminal record. This will scale up restorative justice programming similar to models currently funded by MOCJ and may serve serious felony, lower level felony and misdemeanor level cases when the victim and the DA both agree the case would be suitable for this type of mediation.

    Read the full commitmentSee it on the tracker

  • POA 15 Restorative Justice In progressOngoing

    Latest update

    MOCJ worked with ISLG to develop and release an RFP for restorative justice programming. Awards were made in 2024. After their first year, CUNY ISLG highlighted 3 aspects of their work that furthered restorative justice: their focus on programming, their emphasis on training and technical assistance, and their focus on fellowships. MOCJ looks forward to Year 2 and furthering restorative justice.

    Budget

    FY25: $6.5 million

    Original commitment

    The City will work with the City Council to increase funding to restorative justice programming, including serious felony, lower level felony and misdemeanor cases that would otherwise result in detention and incarceration. This model will invest in community-based infrastructure when appropriate and necessary in conjunction with the District Attorneys and courts to allow for individuals charged with a crime to enter into a community-based restorative justice disposition of their case. In many cases, they will have the opportunity to get the arrest records sealed and have no criminal record going forward when they successfully complete the program. The City agrees that at least (1) such program should operate with the courts and at least one (1) such program should operate independently in the community.

    Read the full commitmentSee it on the tracker

  • POA 16 Community Justice Innovation Fund In progressOngoing

    Latest update

    city funding match is dependent on private dollars. MOCJ continues to work with partners to find appropriate funding sources.

    Budget

    No allocated budget.

    Original commitment

    The Community Justice Innovation Fund would be a public-private partnership that would explore and foster new funding opportunities across government, philanthropy and private sectors that would help the city implement innovative ideas, policies, programming and research. This program would be run out of the Mayor’s Fund and would seek to strengthen the fabric of community justice and safety by focusing on truly community-based investments. The Community Justice Innovation Fund will be a dollar-for-dollar match between the City and private philanthropy up to an amount to be agreed upon between the City and the Council.

    Read the full commitmentSee it on the tracker

Construction

Current Construction updates

Current construction advisories, community meeting dates and project updates are posted on the borojails website.

Questions

Brooklyn questions

Why is the city building a facility in Brooklyn?

Closing Rikers means replacing it with a smaller system in the boroughs. A Brooklyn facility keeps people near the Brooklyn courts, their lawyers, and their families, instead of on an island that is hard to reach.

When will the Brooklyn facility open?

The Brooklyn facility is scheduled to open in 2029.

How will the Brooklyn community space be used?

30,000 square feet is set aside for street-level community space, distinct from the jail and with its own entrance. Its community purposes and services will be developed with local feedback.

Who do I contact about Brooklyn construction?

The Brooklyn Community Construction Liaison: (516) 846-9314, [email protected].

All questions and answers

Archive

From the Brooklyn archive

Construction bulletins, monitoring reports and meeting materials the program published about this site, kept for the record.

346 items, newest first · page 1 of 44

Open the full archive in Resources

all four

Borough-based jails

A fundamental component to the closure of Rikers Island is developing the capacity to house individuals in custody of the Department of Correction off-island, in facilities that are safer and more humane.

See all four facilities Read the full report