In progressIn progress / Committed to contract

Latest update

The protection of street trees was included as requirement in the Queens Garage and Community Space and Queens Dismantle/Swing Space contracts and is included as a requirement in the Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

Status as reported

In progress - included in facility design-build contract

Lead agency

DDC

Budget

POA 6 is part of the overall allocation for the Queens Borough Based Jail, amounting to $3.985 billion.

Original commitment

Existing street trees will be protected, and all work would be performed in compliance with Local Law 3 of 2010 and the NYC Parks Tree Protection Protocol approved by the NYC Parks Borough-specific Forester, to minimize potential adverse impacts to existing trees that will remain in place.