Latest update
Mitchel, Mott Haven, and Patterson: all completed. Construction at Mill Brook started 11/2024; projected for completion in Q4/2026.
Status as reported
Ongoing
Lead agency
NYCHA
Budget
$37,000,000
Original commitment
The city will work with NYCHA to add lighting throughout Mill Brook, cameras at Buildings 1, 2, 3, and 10 at Mill Brook, lighting and cameras at Mitchell Houses, and play equipment to be installed at Mill Brook, Mitchell, Mott Haven, and Patterson Houses.
See it on the tracker See it on the map All Bronx commitments