The Manhattan facility

124-125 White Street. One of four borough facilities that will replace Rikers, near the Manhattan courts and the families and services people rely on.

Track Manhattan commitments Construction updates

Rendering of the Manhattan facility tower on White Street, seen from Collect Pond Park

The building

About the Building

The Manhattan facility will hold people with cases from Manhattan close to the borough's courts, so they can stay connected to lawyers, family, and services while their case moves forward.

Rendering of the facility rising beyond the trees of Columbus Park, beside older stone buildings
View from Columbus Park
Where is it?
124-125 White Street, Manhattan
Get directions (opens in a new tab)
How big is it?
1,040 beds
Community space
20,000 sq ft of street-level community space, including frontage along the new White Street arcade, distinct from the jail and with its own entrance. Its community purposes and services will be developed with local feedback.
When will it open?
Scheduled to open in 2032.
Who do I contact about construction?
Community Construction Liaison: (646) 933-1920, [email protected].
When are community meetings?
Dates and advisories are posted with the construction updates below.

The plan

Where this fits in The plan

The four borough facilities are one part of the plan to close Rikers. The others change how the jails are run, keep more people out of jail, and plan for the island's future.

  1. This facility

    Safer facilities

    Opening new facilities that are safer and more humane, in locations closer to courts and public transportation. This facility is one of them.

  2. Modernizing the DOC

    Restructuring and modernizing the Department of Correction to ensure that the operational challenges faced at Rikers Island are not transferred to the new facilities

  3. Fewer People in Jail

    Fewer case delays, targeted release, diversion, and fewer people returning to jail mean fewer people held, for less time.

  4. The future after closing

    Planning for the Future Reuse of Rikers Island, with a focus on climate resilience, sustainability and renewable energy.

Commitments

What the city promised Manhattan

The Points of Agreement for Manhattan, at the site and across the neighborhood. Open any commitment for the latest update, budget, and original language. Statuses are from the city's November 2026 update.

Open in the tracker
  • Delivered
  • In progress
  • Pending

At the facility site

  • POA 1 Reduced Height and Density of the Jail DeliveredComplete

    Latest update

    Plans include significant reduction from initial proposals. The design-build teams will continue to seek further opportunities for efficiency in construction.

    Budget

    POA 1 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    The final approved maximum building height is 295 feet and the maximum density is a Floor Area Ratio (FAR) of 10.11. This represents a significant reduction from the initial proposal in the Draft Environmental Impact Statement, which proposed a height of 450 feet and a density of 13.1 FAR.

    Read the full commitmentSee it on the tracker

  • POA 2 Provision of Community Facility or Commercial Space (20,000 sq ft) In progressIn progress - included in facility design-build contract

    Latest update

    The Manhattan Facility contract includes the requirement to provide 20,000 square feet of space for future use as a community facility or retail space, currently undefined. A portion of that space is required to be provided along either side of the new White Street arcade. The use of this space will be determined at a later time with input from the community.

    Budget

    POA 2 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    The project will include the construction of 20,000 square feet of community facility or commercial space. The City will work with the Council and the community to shape the use of this space. This space will line either side of the new White Street to activate the pedestrian arcade and front Baxter Street to better integrate the project into the existing commercial corridor.

    Read the full commitmentSee it on the tracker

  • POA 3 Design Consultation In progressIn progress - included in facility design-build contract

    Latest update

    The city will hold a series of community design input workshops and Manhattan Community Board 1 meetings to collect input on the Manhattan Facility design as it develops. The city will continue to meet regularly with Councilmembers, Community Boards, community members, and advocates in Manhattan throughout construction to discuss construction updates and quality of life impacts.

    Budget

    POA 3 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    Upon ULURP completion, the City will provide regular updates on delivery schedule, design, and construction developments and engagement on programmatic progress to Council Members in each respective borough. The City will reconvene the Neighborhood Advisory Committees in Queens, Brooklyn, and the Bronx and the Joint Task Force in Manhattan within 60 days of ULURP passage and will hold regular meetings with updates on time lines, plans, and the like. Finally, DDC and the program management consultant will hold hands-on design engagement workshops that are timed in order to ensure community input is included in the eventual RFP(s).

    Read the full commitmentSee it on the tracker

  • POA 4 Parking In progressIn progress - included in facility design-build contract

    Latest update

    The Manhattan Facility contract requires the provision of 125 accessory parking spaces for DOC staff and authorized service providers.

    Budget

    POA 4 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    125 accessory parking spaces for DOC staff and authorized service providers will be provided below-grade in order to limit the impact to on-street parking in the community.

    Read the full commitmentSee it on the tracker

  • POA 5 Moving the vehicular entrance from Baxter Street to Centre Street DeliveredComplete

    Latest update

    Complete

    Budget

    Complete (No budget allocation for this item.)

    Original commitment

    The City will submit a follow-up action, subject to the required land use approvals, and environmental review as appropriate, to relocate the vehicular entrance of DOC authorized vehicles from Baxter Street to Centre Street in response to community concern regarding the proximity to the entrance to the senior housing facility located at 96 Baxter Street.

    Read the full commitmentSee it on the tracker

  • POA 6 Construction Coordination (Community Construction Liaison) DeliveredComplete, will continue through construction completion

    Latest update

    Manhattan Community Construction Liaison CCL Mobile: (646) 933-1920 Email: [email protected] CCL Office: 75 Baxter Street, New York, NY 10013

    Budget

    POA 6 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    DDC will establish an office near each project site to provide site-specific information and address community complaints and concerns.

    Read the full commitmentSee it on the tracker

  • POA 7 Street Trees In progressIn progress - included in facility design-build contract

    Latest update

    The protection of street trees was included as requirement in the Manhattan Dismantle contract and is included as a requirement in the Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 7 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    Existing street trees will be protected, and all work would be performed in compliance with Local Law 3 of2010 and the NYC Parks Tree Protection Protocol approved by the NYC Parks Borough-specific Forester, to minimize potential adverse impacts to existing trees that will remain in place.

    Read the full commitmentSee it on the tracker

  • POA 8 Air Quality and Noise Monitoring In progressIn progress - included in facility design-build contract

    Latest update

    Air quality and noise monitoring was conducted during the Manhattan Dismantle project, and is included as a requirement in the Manhattan Facility contract. The project's design builders are required to comply with all federal, state, and local laws.

    Budget

    POA 8 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    The DDC will conduct air quality and noise monitoring to limit community impacts and provide for compliance with all applicable regulations.

    Read the full commitmentSee it on the tracker

  • POA 9 Traffic Mitigation In progressIn progress - included in facility design-build contract

    Latest update

    A CTMP was included as a requirement in the Manhattan Dismantle contract and is included in the Facility Design-Build contract. Part of the CTMP will be a monitoring plan for traffic which could provide for additional traffic control measures if deemed necessary.

    Budget

    POA 9 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    A Construction Transportation Monitoring Plan (CTMP) will be initiated at the start of construction for the project work area and, if necessary, additional traffic control measures will be implemented.

    Read the full commitmentSee it on the tracker

  • POA 10 Protecting Open Space In progressIn progress - included in facility design-build contract

    Latest update

    Open space resources were not used for staging or other construction activities during the Manhattan Dismantle project. As defined in the Manhattan Facility contract, the project design-builder will not be permitted to use open space resources for staging or other construction activities during facility construction.

    Budget

    POA 10 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    No open space resources will be used for staging or other construction activities.

    Read the full commitmentSee it on the tracker

  • POA 11 Scaffolding (umbrella scaffolding on Baxter and Centre) In progressIn progress - included in facility design-build contract

    Latest update

    Umbrella-style scaffolding was used during the Manhattan Dismantle/Swing Space project. The Manhattan Facility contract requires the use of umbrella scaffolding along Baxter Street and Centre Street.

    Budget

    POA 11 is part of the overall allocation for the Manhattan Borough Based Jail, amounting to $3.764 billion.

    Original commitment

    The Department of Design and Construction will provide for Umbrella Scaffolding along Baxter and Centre Street to minimize the impacts of scaffolding on the visibility of small businesses.

    Read the full commitmentSee it on the tracker

In the neighborhood

  • POA 12 Support the acquisition and construction of a permanent museum and a new performing arts space DeliveredComplete

    Latest update

    Complete

    Budget

    FY20: $5 million FY21: $15 million FY22: $15 million Total: $35 million

    Original commitment

    The Museum of Chinese in America (MOCA) has been a cultural anchor for the community in Chinatown. In order to secure a permanent home in Chinatown, and to provide a new performing arts space for local Chinese music, dance, and theater groups, the City will invest significant public funding alongside private investments, towards the acquisition and construction of a permanent museum home and a new performing arts space for Chinese music, dance, and theater groups at 215 Centre Street.

    Read the full commitmentSee it on the tracker

  • POA 13 Invest in upgrades in Columbus Park In progressIn progress

    Latest update

    The design phase is wrapping up and the project is now close to procurement. The estimated design completion for the M&O building scope is end of 2026.

    Budget

    Total allocated: $16 million

    Original commitment

    The City will fund renovations and upgrades to the comfort station (including the restrooms, roof, facade, and maintenance and operating) and the pavilion at Columbus Park. DPR will also explore collaboration with Chinatown BID on maintenance and security.

    Read the full commitmentSee it on the tracker

  • POA 13a Invest in upgrades in Columbus Park Pavilion In progressIn progress

    Latest update

    The Columbus Park Pavillion project is in post-design and is awaiting final permitting approvals. Procurement is anticipated to begin in winter.

    Budget

    Allocated: $9.5 million

    Read the full commitmentSee it on the tracker

  • POA 13b Invest in upgrades in Columbus Park M&O Building In progressIn progress

    Latest update

    Parks has expanded scope and funding to address security concerns around the building. The estimated design completion for the M&O building scope is end of 2026.

    Budget

    Allocated: $6.5Million

    Read the full commitmentSee it on the tracker

  • POA 14 Senior Housing Preservation (Chung Pak, 96 Baxter Street) PendingDelayed

    Latest update

    HPD approved a CP for $8M in city Capital funding for the project in FY21, and an additional $4M in FY25, but the project has experienced delays related to issues with the project GC and in obtaining additional federal approvals required to access additional funding and complete the scope of work. HPD is working with HUD to secure the necessary funding to move the project forward. The project closed in November 2025. As of January 12th, construction has not started.

    Budget

    $12M in City capital has been allocated to the project.

    Original commitment

    The City agrees that the long-term preservation of senior housing at Chung Pak (96 Baxter Street) is important and will work with the organization to develop a preservation deal through HPD. The deal will include a long-term loan to address capital upgrades needed in the building. The City will also address HVAC and window upgrades as part of the HPD preservation deal, subject to a physical needs assessment. The City will commit to a ground lease PILOT abatement for the term of the lease, subject to review of the physical needs assessment and building finances, consistent with the terms of an HPD preservation deal, and subject to any approvals that may be necessary.

    Read the full commitmentSee it on the tracker

  • POA 15 Improvement of Chung Pak Outdoor Terrace PendingDelayed

    Latest update

    HPD approved a CP for $8M in city Capital funding for the project in FY21, and an additional $4M in FY25, but the project has experienced delays related to issues with the project GC and in obtaining additional federal approvals required to access additional funding and complete the scope of work. HPD is working with HUD to secure the necessary funding to move the project forward. The project closed in November 2025. As of January 12th, construction has not started.

    Budget

    $12M in City capital has been allocated to the project.

    Original commitment

    In order to preserve a comfortable outdoor place for senior residents of 96 Baxter Street to relax, the City will fund the construction of an enclosure on the terrace of the building through an HPD preservation deal.

    Read the full commitmentSee it on the tracker

  • POA 16 Rent credits to be issued to Chung Pak and relocation assistance for small business tenants DeliveredComplete

    Latest update

    DCAS has successfully obtained Borough Board approval and mayoral approval for the execution of the Chung Pak lease amendment related to the BBJ plan. The lease is currently pending execution by the city and tenant.

    Budget

    Buy-outs were completed in 2021, and those tenants have long-since vacated.

    Original commitment

    The rent due to the City from Chung Pak under the commercial lease for space located under the Manhattan Detention Center (Block 198, Lot 1) and within the residential building at 124/125 White Street (Block 167, Lot 1) will be abated during the construction period. The City will further support Chung Pak's negotiated buyouts with all small businesses that have leases with Chung Pak signed as of October 16, 2019 that extend through the start of construction. Additionally, the City will seek to extend the commercial lease with Chung Pak to 2078. The City will also provide capitally-eligible fit- out for small business tenants returning to the building at the end of the construction period, subject to any approvals that may be necessary.

    Read the full commitmentSee it on the tracker

  • POA 17 Install a lift/elevator at 70 Mulberry Street In progressOngoing

    Latest update

    DCAS continues to coordinate with its tenants and DDC regarding the rebuild. Three elevators are part of the project. DDC issued a Notice to Proceed (NTP) to Hunter Robert ZD Jasper Joint Venture, the CM-Build company to manage the construction in Fall 2026. Construction is anticipated to start in Q1 2027.

    Budget

    $184 million

    Original commitment

    Chinatown Manpower provides a range of programs for the local community at 70 Mulberry Street. To make these programs more accessible for all people, the City will construct a new lift/elevator in the building.

    Read the full commitmentSee it on the tracker

Construction

Current Construction updates

Current construction advisories, community meeting dates and project updates are posted on the borojails website.

Questions

Manhattan questions

Why is the city building a facility in Manhattan?

Closing Rikers means replacing it with a smaller system in the boroughs. A Manhattan facility keeps people near the Manhattan courts, their lawyers, and their families, instead of on an island that is hard to reach.

When will the Manhattan facility open?

The Manhattan facility is scheduled to open in 2032.

How will the Manhattan community space be used?

20,000 square feet is set aside for street-level community space, including frontage along the new White Street arcade, distinct from the jail and with its own entrance. Its community purposes and services will be developed with local feedback.

Who do I contact about Manhattan construction?

The Manhattan Community Construction Liaison: (646) 933-1920, [email protected].

All questions and answers

Archive

From the Manhattan archive

Construction bulletins, monitoring reports and meeting materials the program published about this site, kept for the record.

357 items, newest first · page 1 of 45

Open the full archive in Resources

all four

Borough-based jails

A fundamental component to the closure of Rikers Island is developing the capacity to house individuals in custody of the Department of Correction off-island, in facilities that are safer and more humane.

See all four facilities Read the full report