In progressIn progress / Committed to contract

Latest update

The city reduced program redundancies across all four sites including a reduction in the required number of accessory parking spaces in Brooklyn to 83 spaces for authorized city vehicles including 5 parking spaces dedicated to the NYPD sally port, thus reducing the cost of the project. The revised parking is analyzed and reflected in the March 2024 technical memorandum available on CEQR Access.

Status as reported

In progress - included in facility final design documents

Lead agency

DDC

Budget

POA 4 is part of the overall allocation for the Brooklyn Borough Based Jail, amounting to $2.959 billion.

Original commitment

292 accessory parking spaces for DOC staff and authorized service providers will be provided below-grade in order to limit the impact to on-street parking in the community.