Latest update
Mott Haven/Mill Brook/Mitchel/Patterson. The work continues with funding approval, pre-construction and abatement processes. Patterson: projected for completion in Q3/2028 Mitchel: projected for completion in Q3/2029 Mott Haven: projected for completion in Q2/2029 Mill Brook: projected for completion in Q1/2028
Status as reported
Ongoing
Lead agency
NYCHA
Budget
$29,895,209.26
Original commitment
The City will work with NYCHA to upgrade the facilities at four developments near the borough-based jail system sites. Renovations will address needs identified in the last Physical Needs Assessment. These include: